Reschedule an Assignment From the Schedule Page

You can change the dates for a scheduled assignment without leaving the Schedule page.

  1. Either move the assignment to a different week or edit the dates without changing the week.
    To do this Do this
    Change the week for which the assignment is scheduled

    Drag the scheduled assignment from the Schedule panel or the Assignments list to a different week.

    Alternatively, in the Schedule panel, click Actions button > Reschedule to Week > Week number beside the assignment you want to change.

    Change the dates without changing the week for which the assignment is scheduled

    In the Schedule panel, double click the assignment you want to change.

    Alternatively, in the Schedule panel, click Actions button > Edit Schedule beside the assignment you want to change.

  2. Update the Due date for the assignment.
  3. Optional: Change the Available or View Until dates.
    Note Available and View Until rules that result in dates either before the course starts or after it ends are not changed, but the calculated dates are changed to either the start or end of the course, respectively.
  4. Click Schedule.

    The assignment is listed under the selected week and the calculated assignment dates are displayed.

If needed, copy the changes for the assignment to other sections.